Repairs to the Anneewakee Creek Bridge on Anneewakee Road are moving along

The approaches to the Anneewakee Creek Bridge on Anneewakee Road have been dug out and steel rebars have been put in place; the forms are not yet installed, but the concrete will be poured tomorrow. The concrete will cure for about 3 days and then back-filling, compaction and paving can proceed.

Even before the flood, this bridge was scheduled to be replaced this year.  Work on the new bridge construction will begin soon, just downstream of the repaired bridge.